CAPM Certified Associate in Project Management Review: Earned Value Management

Review earned value management for this CAPM Certified Associate in Project Management question with the key prompt clue, correct-answer reasoning, distractor checks, and sources to verify next.

Practice this exact exam Back to Resource Center

This question-specific review guide is tied to the answer reasoning for a PracticeTestVault item. Use it after you answer the question so the review stays focused on what the prompt actually tested.

What this question is testing

Objective: Earned Value Management

Prompt focus: A project has a planned value of 50,000 dollars and an earned value of 45,000 dollars. The schedule variance is:

Why the correct answer works

Negative 5,000 dollars

Correct. SV equals EV minus PV, which is 45,000 minus 50,000, equaling negative 5,000 dollars.

Why the tempting wrong answer fails

The tempting wrong answer usually loses because it skips the key condition, priority, or evidence in the prompt.

Plain-language takeaway

Schedule variance equals earned value minus planned value: 45,000 minus 50,000 equals negative 5,000 dollars, indicating the project is behind schedule.

Simple analogy

Think of earned value management like following a short checklist: identify the clue, confirm the rule, and then make the move that fits this exact scenario.

How to review it before a retake

  • Underline the command word and name what the question is asking before rereading the choices.
  • Compare the correct answer against the closest distractor and write the exact detail that separates them.
  • Retest this objective with a fresh question without looking at the rationale first.