CAPM Certified Associate in Project Management Review: Procurement Management

Review procurement management for this CAPM Certified Associate in Project Management question with the key prompt clue, correct-answer reasoning, distractor checks, and sources to verify next.

Practice this exact exam Back to Resource Center

This question-specific review guide is tied to the answer reasoning for a PracticeTestVault item. Use it after you answer the question so the review stays focused on what the prompt actually tested.

What this question is testing

Objective: Procurement Management

Prompt focus: A contract type in which the buyer pays the seller for actual costs plus a fixed fee is called a:

Why the correct answer works

Cost plus fixed fee contract

Correct. A cost plus fixed fee contract reimburses actual costs and adds a fixed fee.

Why the tempting wrong answer fails

Incorrect. A time and materials contract bills hourly rates and materials, not cost plus a fixed fee.

Plain-language takeaway

A cost plus fixed fee contract reimburses the seller for allowable costs and adds a predetermined fixed fee that does not change with performance.

Simple analogy

Think of procurement management like following a short checklist: identify the clue, confirm the rule, and then make the move that fits this exact scenario.

How to review it before a retake

  • Underline the command word and name what the question is asking before rereading the choices.
  • Compare the correct answer against the closest distractor and write the exact detail that separates them.
  • Retest this objective with a fresh question without looking at the rationale first.