PracticeTestVault review illustration for Calculate a PERT expected duration on PMI Scheduling Professional (PMI-SP) Review: Calculate a PERT expected duration

PracticeTestVault resource center

PMI Scheduling Professional (PMI-SP) Review: Calculate a PERT expected duration

Review calculate a pert expected duration for this PMI Scheduling Professional (PMI-SP) question with the key prompt clue, correct-answer reasoning, distractor checks, and sources to verify next.

Practice this exact exam Back to Resource Center

This question-specific review guide is tied to the answer reasoning for a PracticeTestVault item. Use it after you answer the question so the review stays focused on what the prompt actually tested.

What this question is testing

Objective: Calculate a PERT expected duration

Prompt focus: An activity has an optimistic duration of 6 days, a most likely duration of 9 days, and a pessimistic duration of 18 days. Using the PERT weighted average, what expected duration should the scheduler use?

Why the correct answer works

10 days

PERT expected duration = (O + 4M + P) / 6 = (6 + 4 x 9 + 18) / 6 = 10 days.

Why the tempting wrong answer fails

The tempting wrong answer usually loses because it skips the key condition, priority, or evidence in the prompt.

Plain-language takeaway

PERT expected duration = (O + 4M + P) / 6 = (6 + 4 x 9 + 18) / 6 = 10 days. Interpret the result in the schedule context before recommending action.

Simple analogy

Think of calculate a pert expected duration like following a short checklist: identify the clue, confirm the rule, and then make the move that fits this exact scenario.

How to review it before a retake

  • Underline the command word and name what the question is asking before rereading the choices.
  • Compare the correct answer against the closest distractor and write the exact detail that separates them.
  • Retest this objective with a fresh question without looking at the rationale first.

Sources to verify next